Forced objection and prevention... What happened with “Electricité du Liban”?
11:33 · 07 November 2026
2 min read
On November 6, 2026, the Electricité du Liban was able to complete the transfer of the transformer from the Jeb Jenin station with the support of the Lebanese Army, in preparation for its installation at the Boulos Arqash station in the coming days, with the aim of restoring the electrical supply to normal in the Jezzine region, Iqlim al-Kharroub and the neighborhood.
The corporation had announced that on September 29, 2026, one of the 20 MVA power transformers broke down. At the Boulos Arqash station in the Litani Department, which supplies large areas of the Jezzine region, Iqlim al-Kharroub and the neighborhood, which has led to a severe shortage of electrical supply in these areas.
The corporation indicated that it attempted to replace the broken transformer with one of the similar spare transformers present at the Jeb Jenin station, but the technical teams were subjected to objection by some residents and local activists, and were forcibly prevented from completing the process of moving the spare transformer, knowing that its transfer does not affect the electrical supply to the Jeb Jenin station and the surrounding areas.
She explained that the backup transformer in Jeb Jenin has a capacity of 20 MVA, and had been in service for several years, pointing out that, due to the need to meet the additional loads at the Jeb Jenin station and the Western Bekaa region, it was replaced with a larger transformer with a capacity of 40 MVA, and the old transformer was put aside to be used as a backup transformer on the Lebanese network where needed.
The Electricité du Liban thanked His Excellency the President of the Republic for his follow-up on this issue, which contributed to overcoming the obstacles and completing the transfer process. It also thanked the security forces, especially the Lebanese Army, for accompanying the technical teams and providing them with the necessary protection during the implementation of the mission.
← Previous article
In Ottawa, Raji discusses support for the Lebanese Army with the Canadian Minister of Defense
Related Articles
“Energy”: Fayyad insists on misleading to evade his responsibilities
Al-Sadi and Salam are in Doha to complete electricity discussions
Abi Khalil criticizes the electricity plan: it reproduces the financial and administrative policies that contributed to the collapse of the sector